The core idea of this page: the site acceptance test answers a different question from the factory test. The FAT asked "does this machine meet its specification?"; the SAT asks "does this machine, on this site, with these utilities and this product, in this line, produce good packs at the required rate?" Those are not the same question, which is why a machine that passed a factory test can fail on site.
What the SAT adds that the FAT cannot
Real utilities
Compressed-air quality and pressure stability, power quality, steam and chilled-water capacity, water hardness, and extraction. A sealing machine that held temperature in a supplier's stable plant can struggle on a site with a weak air supply or a voltage dip at shift start.
Real product and material
Product from actual production, with the real variation in viscosity, particle size, fill temperature and film lot. Film lot variation alone explains a large share of on-site seal problems.
Real integration
Handshakes with the upstream filler and downstream case packer, conveyor height and gap, accumulation logic, line control and MES/SCADA interfaces. Integration faults are the most common reason a SAT slips.
Test the unhappy paths as well as the happy ones: blocked downstream, starved upstream, an operator pressing stop mid-cycle, a power dip and recovery, and a product change while the line is running. These are the states where handshakes fail, and they are exactly the states a factory test cannot reproduce because the factory line around the machine is not the buyer's line.
Real environment
Ambient temperature, humidity, dust, washdown and vibration. These affect adhesive behaviour, sensor reliability and fill accuracy.
Writing the SAT protocol
The protocol should be written before installation, not after. It needs: scope per machine and per format; the utilities to be verified with their acceptable ranges; the product and material lots to be used; the performance run length; pack-quality tests with sample sizes and pass limits; the integration tests; and the documentation to be handed over.
Where the FAT already proved a criterion, the SAT can reduce sample size but should not skip it — the point is to prove the result transfers.
Sequence of a well-run SAT
Installation verification
Level, alignment, guarding, anchorage, and that the as-built machine matches the drawings and the FAT configuration. Photograph the installation before commissioning.
Utility verification
Measure, do not assume: air pressure and dew point at the machine inlet, supply voltage and phase balance, seal-jaw heat-up time and stability, water flow and temperature. Record the values.
Dry commissioning
Run the sequence with no product, then with dummy product, checking every sensor, interlock and stop category. Confirm safety functions before anyone runs production.
Performance run
Run at rated speed for the agreed duration on the buyer's product, with the stop and reject log attached. Count small stops, not just stoppages over a threshold.
Pack quality and handover
Run the agreed pack tests, retain samples, then hand over documentation, spares, training records and the signed protocol with the punch list.
Training and competency
Acceptance is not complete while only the supplier's engineer can run the machine. The SAT should include operator training on the actual formats, a demonstrated changeover by the buyer's crew, a cleaning cycle performed by the buyer, and a basic fault-finding walkthrough of the alarm list. Record who was trained and on which date; auditors ask for it later.
Documentation package
Handover documentation should include as-built drawings, electrical schematics, pneumatic diagrams, spare-parts list with recommended spares, PLC and HMI backups, calibration certificates, material certificates, the validated parameter set per format, and the signed protocol with its punch list. A machine without a parameter backup loses its validated settings the first time someone replaces a controller.
Closing the punch list
Any item that cannot be fixed during the visit is recorded with an owner, a date and an agreed interim control — for example a manual check that substitutes for a missing sensor. Interim controls must be written into the operating procedure, not remembered by whoever was in the room, otherwise they quietly disappear at the first shift change.
Site-specific failure modes
The recurring ones: utilities out of specification discovered after the supplier has left; product that behaves differently from the sample used at the factory; film lot variation causing seal failures that appear only after hours of running; conveyor interface faults; and operators trained on a machine that then gets re-parameterised during commissioning without retraining.
Ramp-up after acceptance
Acceptance and ramp-up are different phases, and conflating them is how lines end up "accepted" while running at seventy percent of target. Plan a ramp-up window with a daily output target, a defined support presence from the supplier, and a review point where the punch list and the OEE baseline are revisited. The SAT proves the machine can perform; the ramp-up proves the organisation can run it.
Verification checklist
Before signing: utilities measured and within range and recorded against the machine inlet rather than the plant header; performance run duration met with stop log attached; pack tests passed with retained samples; integration handshakes demonstrated; documentation and spares handed over; operators trained and records kept; punch list closed or scheduled with owners and dates.
Source: Acceptance testing — Wikipedia
"In engineering and its various subdisciplines, acceptance testing is a test conducted to determine if the requirements of a specification or contract are met."
Frequently asked questions
Can the SAT be combined with the FAT?
No. They test different things: factory conditions versus site conditions. Combining them hides utility and integration problems until after acceptance.
What if the product is not available on site yet?
Use the closest available substitute, document the difference, and plan a retest with real product. Do not close the SAT on a substitute without written risk acceptance.
How long after installation should the SAT run?
Long enough to include a real start-up, a shift change and a cleaning cycle — typically several days of production, not a single afternoon.
Related reading: FAT and SAT guide, factory acceptance test, OEE, and the end-of-line packaging category.
Related guides
- End-of-Line Machines: Top 10 Compared (2026) — Ten end-of-line machines compared across case packing, palletizing, sh…
- Case Packing vs Palletizing: Which to Automate First — case packing and palletizing are two different automation decisions — …
- Conventional vs Robotic Palletizing — conventional (layer) palletizers build a whole layer at once and win o…
- Shrink Wrapping vs Stretch Hooding — shrink wrapping and stretch hooding both stabilize a pallet load with …
- Packaging Line Design and Integration Guide: Plan a Line That Runs — a packaging line is designed from the product out, not from the machin…
- FAT and SAT for Packaging Machinery: Acceptance Testing Explained — FAT and SAT are the two acceptance gates that transfer risk from the s…
- Packaging Line OEE and Downtime Analysis: Measure the Losses That Matter — OEE turns a vague “the line is down too much” into three m…
- How a Case Packer Works — a case packer takes individual packs and builds them into a shipping c…